Warnowquerung GmbH & Co. KG would like to inform all tunnel users that today marks the start of the construction work to renovate the asphalt in the north tube of the Warnowtunnel.
The construction site is expected to remain open until 28.05.2025. During the five weeks of construction work by STRABAG, traffic from both directions will be routed through the south tube at reduced speed.
Once again, the Warnowtunnel will remain passable in both directions at all times during the entire construction work.
We wish all tunnel users a safe and pleasant journey!